Snapshot

Location: Melbourne
Client(s): Veneziano Coffee Roasters
Scope: Complete installation of a coffee roasting and production line
Timeline: 6-month program
Team: Mechanical plumbers, electricians

Client Snapshot photo
$850K
Value of project
6,000
Hours committed
2
Number of disciplines
9mo
Completion period
Client

Client

Veneziano Coffee Roasters, one of Australia’s leading coffee brands, was seeking to install a new coffee roasting machine and production line at their facility. The equipment, supplied by Brambati, included complex machinery and processes essential to their production of premium coffee. Veneziano’s required the installation to be complete within a very specific timeframe so as not to set their operations back.

Challenge

The most notable challenge was the Single Line Diagrams (SLDs) that were provided in Italian, meaning before we could use them, we needed to translate them for use in practical application. 

The installation was also very complex and involved multiple distinct stages that all needed to be completed to the highest of standards, on time, so the client could meet its production deadlines.

Challenge
Why they chose us

Why they chose us

Veneziano Coffee Roasters selected us based on our proven expertise with Brambati systems and previous successful installations of coffee roasters and production lines, in addition to our multidisciplinary capacity. While this project was already quite unique, adding the Italian SLDs added a new dimension, and the client trusted us to successfully deliver in line with their schedule. 

How we did it

We approached this project with a real focus on teamwork and taking advantage of our diverse skills:

  • Accurate translation: The Italian SLDs were carefully translated and adapted into practical, actionable designs that met Australian standards.
  • Comprehensive process: We implemented an end-to-end installation, including bulk bag unloading, green bean storage, a 600kg coffee roaster, and packaging.
  • Project coordination: We set ourselves strict deadlines within the broader project plan and seamlessly passed the baton to achieve them. 

The outcome

We successfully delivered: 

  • A fully operational production line. 
  • Seamless integration of Brambati machinery.
  • End-to-end installation achieved within the client's strict timeframes.

Our client was pleased with the outcome, and the confidence it gave them to meet production schedules and fulfil the requirements of their own clients. 